Construction contracts, слайд №1Construction contracts, слайд №2Construction contracts, слайд №3Construction contracts, слайд №4Construction contracts, слайд №5Construction contracts, слайд №6Construction contracts, слайд №7Construction contracts, слайд №8Construction contracts, слайд №9Construction contracts, слайд №10Construction contracts, слайд №11Construction contracts, слайд №12Construction contracts, слайд №13Construction contracts, слайд №14Construction contracts, слайд №15Construction contracts, слайд №16Construction contracts, слайд №17Construction contracts, слайд №18Construction contracts, слайд №19Construction contracts, слайд №20

Вы можете ознакомиться и скачать презентацию на тему Construction contracts. Доклад-сообщение содержит 20 слайдов. Презентации для любого класса можно скачать бесплатно. Если материал и наш сайт презентаций Mypresentation Вам понравились – поделитесь им с друзьями с помощью социальных кнопок и добавьте в закладки в своем браузере.

Слайды и текст этой презентации


Слайд 1





Construction Contracts
Описание слайда:
Construction Contracts

Слайд 2





G 3. Construction Contracts
Types of contracts
Recognition methods :
Presentation :
Описание слайда:
G 3. Construction Contracts Types of contracts Recognition methods : Presentation :

Слайд 3





IAS 11 (International Accounting Standards)
Construction Contracts
 provides requirements on the allocation of contract revenue and contract costs to accounting periods in which construction work is performed.
Objective of IAS 11 is to prescribe the accounting treatment of revenue and costs associated with construction contracts.
Описание слайда:
IAS 11 (International Accounting Standards) Construction Contracts  provides requirements on the allocation of contract revenue and contract costs to accounting periods in which construction work is performed. Objective of IAS 11 is to prescribe the accounting treatment of revenue and costs associated with construction contracts.

Слайд 4





History of IAS 11 — Construction Contracts
Описание слайда:
History of IAS 11 — Construction Contracts

Слайд 5





TYPES OF CONSTRUCTION CONTRACTS

Two broad categories:
Price Given in Advance Contracts (Priced-based Contracts)
Cost Reimbursement Contracts (Cost-based Contracts)
Factors Influencing the Choice of the Type of Contract
The appropriateness for providing an adequate incentive for efficient performance by the contractor
The ability to introduce changes
The allocation of risks
The start and completion date of the project
Описание слайда:
TYPES OF CONSTRUCTION CONTRACTS Two broad categories: Price Given in Advance Contracts (Priced-based Contracts) Cost Reimbursement Contracts (Cost-based Contracts) Factors Influencing the Choice of the Type of Contract The appropriateness for providing an adequate incentive for efficient performance by the contractor The ability to introduce changes The allocation of risks The start and completion date of the project

Слайд 6





TYPES OF CONSTRUCTION CONTRACTS

1. Lump Sum Contact
2. Contract based on a Bill of Quantities
Sometimes called Unit Price Contract
3. Schedule of Rates Contract
4. Cost plus Percentage of Cost
5. Cost plus Fixed Fee
6. Target Cost with Variable Fees Contract
7. Guaranteed Maximum Price Contract (GMP)
Описание слайда:
TYPES OF CONSTRUCTION CONTRACTS 1. Lump Sum Contact 2. Contract based on a Bill of Quantities Sometimes called Unit Price Contract 3. Schedule of Rates Contract 4. Cost plus Percentage of Cost 5. Cost plus Fixed Fee 6. Target Cost with Variable Fees Contract 7. Guaranteed Maximum Price Contract (GMP)

Слайд 7





1. Lump Sum Contact

Main Aspects 
1. Payment may be staged at intervals of time.
2. The contractor is responsible for preparing his B.O.Q. 
3. The responsibility is on the contractor to include in his price everything necessary for carrying out the work.  
Описание слайда:
1. Lump Sum Contact Main Aspects 1. Payment may be staged at intervals of time. 2. The contractor is responsible for preparing his B.O.Q. 3. The responsibility is on the contractor to include in his price everything necessary for carrying out the work.  

Слайд 8





1. Lump Sum Contact

Advantages 
The final price is known
The contractor has more incentive to reduce his cost to increase the profit.
The contractor hopes to complete the job as quickly as possible.
Disadvantages 
Changes can be very expensive and source of trouble. 
The contractor carries much of the risks. 
Competent contractors may decide not to bid to avoid a high-risk lump sum contract.
Описание слайда:
1. Lump Sum Contact Advantages The final price is known The contractor has more incentive to reduce his cost to increase the profit. The contractor hopes to complete the job as quickly as possible. Disadvantages Changes can be very expensive and source of trouble. The contractor carries much of the risks. Competent contractors may decide not to bid to avoid a high-risk lump sum contract.

Слайд 9





2. Contract based on a Bill of Quantities
Sometimes called Unit Price Contract

Main Aspects 
Items of work of the contract are specified with estimated quantities 
Estimated quantities are surveyed by Architect/Engineer.
Contractors enter unit prices against the estimated quantities of work.
The contract is based on estimated quantities of work items.
Payment is made on the basis of units of work actually done.
Описание слайда:
2. Contract based on a Bill of Quantities Sometimes called Unit Price Contract Main Aspects Items of work of the contract are specified with estimated quantities Estimated quantities are surveyed by Architect/Engineer. Contractors enter unit prices against the estimated quantities of work. The contract is based on estimated quantities of work items. Payment is made on the basis of units of work actually done.

Слайд 10





2. Contract based on a Bill of Quantities
Sometimes called Unit Price Contract

Advantages
1. Saving the heavy cost of preparing many bills of quantities by the contractors.
2. Fair basis for competition.
Changes in contract documents can be made easily by the owner.
Lower risk for contractor.
Disadvantages 
1. The exact final price of the project is not known to the owner until the completion of the project.
Описание слайда:
2. Contract based on a Bill of Quantities Sometimes called Unit Price Contract Advantages 1. Saving the heavy cost of preparing many bills of quantities by the contractors. 2. Fair basis for competition. Changes in contract documents can be made easily by the owner. Lower risk for contractor. Disadvantages 1. The exact final price of the project is not known to the owner until the completion of the project.

Слайд 11





3. Schedule of Rates Contract

Main Aspects 
1. A Schedule of the work items without quantities.
2. The descriptions of items and the units of measurement are similar to those used in a normal B.O.Q., but no quantities are given.
3. It is common for separate rates to be quoted for labor, plant, and materials.
4. Used for repair and maintenance works or under conditions of urgency.
Описание слайда:
3. Schedule of Rates Contract Main Aspects 1. A Schedule of the work items without quantities. 2. The descriptions of items and the units of measurement are similar to those used in a normal B.O.Q., but no quantities are given. 3. It is common for separate rates to be quoted for labor, plant, and materials. 4. Used for repair and maintenance works or under conditions of urgency.

Слайд 12





3. Schedule of Rates Contract

Advantages 
1. Work can be commenced earlier than if a full B.O.Q has been prepared.
Disadvantage 
1. No indication of the final price of the works.
2. Very difficult to determine which contractor submitted the most advantageous offer.
3. May cause financial problems to the public owners.
Описание слайда:
3. Schedule of Rates Contract Advantages 1. Work can be commenced earlier than if a full B.O.Q has been prepared. Disadvantage 1. No indication of the final price of the works. 2. Very difficult to determine which contractor submitted the most advantageous offer. 3. May cause financial problems to the public owners.

Слайд 13





4. Cost plus Percentage of Cost

Main Aspects 
1. The contractor is reimbursed for all his costs with a fixed % age of costs to cover his services.
2. Project/site overheads may be covered by the % age or computed as one of the costs.
Описание слайда:
4. Cost plus Percentage of Cost Main Aspects 1. The contractor is reimbursed for all his costs with a fixed % age of costs to cover his services. 2. Project/site overheads may be covered by the % age or computed as one of the costs.

Слайд 14





4. Cost plus Percentage of Cost

Advantages 
1. Construction can start before design is completed.
2. If the contractor is efficient in the utilization of resources then the cost to the client should represent a fair price for the work undertaken.
Disadvantages 
1. The total cost is completely unknown before start.
2. No incentive for the contractor to be efficient.
3. Minimum efficiency maximizes the profit.
4. Owner must exercise tight cost control.
Описание слайда:
4. Cost plus Percentage of Cost Advantages 1. Construction can start before design is completed. 2. If the contractor is efficient in the utilization of resources then the cost to the client should represent a fair price for the work undertaken. Disadvantages 1. The total cost is completely unknown before start. 2. No incentive for the contractor to be efficient. 3. Minimum efficiency maximizes the profit. 4. Owner must exercise tight cost control.

Слайд 15





5. Cost plus Fixed Fee
Main Aspects 
1. The owner pays all costs of construction with a fixed sum of money.
2. The work must be fairly well defined by the owner.
Advantages 
1. There is no incentive for the contractor to inflate costs.
2. There is incentive for the contractor to complete the work as quickly as possible.
Disadvantages 
Major variations create problems. 
The speed of commencing the work is undermined since before a fee can be agreed a fairly detailed description of work must be made.
Описание слайда:
5. Cost plus Fixed Fee Main Aspects 1. The owner pays all costs of construction with a fixed sum of money. 2. The work must be fairly well defined by the owner. Advantages 1. There is no incentive for the contractor to inflate costs. 2. There is incentive for the contractor to complete the work as quickly as possible. Disadvantages Major variations create problems. The speed of commencing the work is undermined since before a fee can be agreed a fairly detailed description of work must be made.

Слайд 16





6. Target Cost with Variable Fees Contract
Main Aspects 
1. The contractor and owner agree to a target estimate of construction.
2. Bonus or penalty arrangements are tied to this target figure.
3. The work must have a fairly definite nature. 
4. Cost target -> sharing of savings
5. Time target -> fixed sum of money for each day.
Описание слайда:
6. Target Cost with Variable Fees Contract Main Aspects 1. The contractor and owner agree to a target estimate of construction. 2. Bonus or penalty arrangements are tied to this target figure. 3. The work must have a fairly definite nature. 4. Cost target -> sharing of savings 5. Time target -> fixed sum of money for each day.

Слайд 17





6. Target Cost with Variable Fees Contract
Advantages 
1. There is an incentive to carry out the work as quickly as possible.
2. The client also stands to benefit through the contactor's efficiency.
Disadvantages 
1. Difficulties may arise in agreeing on a revised target cost if there are major variations or cost inflation.
2. A tight cost control must be exercised, which may be difficult and/or costly.
Описание слайда:
6. Target Cost with Variable Fees Contract Advantages 1. There is an incentive to carry out the work as quickly as possible. 2. The client also stands to benefit through the contactor's efficiency. Disadvantages 1. Difficulties may arise in agreeing on a revised target cost if there are major variations or cost inflation. 2. A tight cost control must be exercised, which may be difficult and/or costly.

Слайд 18





7. Guaranteed Maximum Price Contract (GMP)
1. The contractor guarantees that he will construct the project in full accordance with the drawings and specifications and that the price to the owner will not exceed some total upset price.
2. If the price of the work exceeds the assured maximum, the contractor pays for the excess.
3. Contracts are often competitively bid in a manner similar to that for lump-sum contracts, but managed as cost plus.
4. The successful bidder is determined on the combined basis of his quoted maximum price and fixed fee.
Описание слайда:
7. Guaranteed Maximum Price Contract (GMP) 1. The contractor guarantees that he will construct the project in full accordance with the drawings and specifications and that the price to the owner will not exceed some total upset price. 2. If the price of the work exceeds the assured maximum, the contractor pays for the excess. 3. Contracts are often competitively bid in a manner similar to that for lump-sum contracts, but managed as cost plus. 4. The successful bidder is determined on the combined basis of his quoted maximum price and fixed fee.

Слайд 19





Recognition methods
Stage of Completion (Percentage of Completion)
Value Based Methods


Cost Based Method
Описание слайда:
Recognition methods Stage of Completion (Percentage of Completion) Value Based Methods Cost Based Method

Слайд 20